Repairs and upgrades at the Zeehan Swimming Pool continue to progress well.
The recent concrete pour was successful, allowing the vinyl liner to be installed this week.
Once the liner installation is completed, contractors will commence works in the plant room.
This has been a long project, and we are nearing the finish line. Once completed the pool infrastructure will have been completely upgraded, including placement of a disability hoist for those patrons who may have mobility issues.